Phase 3 Progress

Timeline

三期整建主要建設時間標杆

2017

開始籌劃日期

向市政府申請及核准日期
向市政府申請及核准日期
從2020到2025年有幾個不同階段的申請,最後的開工允許証於2025年5月取得

May 2025 取得
Nov 2023 開始

工程招標日期

開始動工日期

July 2025
Aug 2025

開工典禮日期

地基完成日期

Nov 2025
Jan 2026

一樓主結構完成日期

二樓主結構完成日期

Mar 2026
May 2026

三樓主結構預計完成日期

預計全棟樓外觀完成日期

Dec 2026
May 2027

預計全棟樓内部裝潢完成日期

預計啓用日期

Aug 2027
目前工程進度 as of April 2026

目前正在建設四樓主結構

PHASE III CAMPUS DEVELOPMENT

Phase III Campus Redevelopment Construction and Fundraising Progress

The Phase III Campus Redevelopment is the final phase of LOGOS Evangelical Seminary’s campus renewal plan.

Following earlier renovations to the Administration Building, Academic Building, classrooms, and library, Phase III will bring the Seminary’s comprehensive campus redevelopment plan to completion. This page provides updates on construction progress and the final stage of fundraising, allowing donors and partners who care about the development of the LOGOS campus to stay informed about current progress and remaining needs.

PROJECT
Final Phase of Campus Redevelopment
CONSTRUCTION
Ongoing Construction Updates
SUPPORT
Final-Stage Fundraising Needs
PHASE III

Upon completion of Phase III, LOGOS Evangelical Seminary’s comprehensive campus redevelopment plan will reach its final stage.

BUILDING OVERVIEW

Building Space Plan

The Phase III building is located directly across from the Administration Building. It is planned as a four-story, multipurpose facility integrating parking, the main entrance, student life, campus fellowship, administrative offices, workspaces, meeting rooms, and other campus needs.

LEVEL 01
Parking and Main Lobby
Planned for parking and primary entrance functions.
LEVEL 02
Seminary Facilities
Planned for LOGOS Evangelical Seminary programs and operations.
LEVEL 03
Seminary Facilities
Planned for LOGOS Evangelical Seminary programs and operations.
LEVEL 04
Office and Meeting Spaces
Planned for offices, meetings, and related functions.
SPACE PROGRAM

Phase III will bring together a wide range of campus spaces, including a student activity center, Seminary history gallery, fellowship lounge, dining area, prayer room, production studio, Student Affairs offices, and additional office and meeting facilities.

ARCHITECTURAL PLANS · FLOOR LAYOUTS
Select a drawing to view it in full size
Phase III floor-by-floor space plan for LOGOS Evangelical Seminary View Drawing ↗
FLOOR PLAN
Phase III Floor-by-Floor Space Plan
01
Phase III functional space plan for LOGOS Evangelical Seminary View Drawing ↗
SPACE PLAN
Phase III Functional Space Plan
02
Phase III architectural floor plan for LOGOS Evangelical Seminary View Drawing ↗
ARCHITECTURAL DRAWING
Phase III Architectural Floor Plan
03
CONSTRUCTION FUNDING

Construction Funding

The original estimated total construction cost was $13.54M, including the building, interior improvements, equipment, and design. Fundraising for this amount has been completed. Following the 2025 wildfires and the effects of inflation, the project is expected to require an additional $1.0M in funding.

ORIGINAL PROJECT
Original estimated construction cost, including the building, interior improvements, equipment, and design
$13.54M FUNDING COMPLETED
ADDITIONAL FUNDING · CURRENT PROGRESS

Final-Stage Additional Funding Progress

AS OF AUGUST 2026
ADDITIONAL TARGET
$1.0M
Additional Funding Goal
RAISED
$0K
Amount Raised
REMAINING
$724K
Remaining Need
Additional Funding Progress
0%
$0 $1.0M GOAL

As of August 2026, the additional funding goal still requires $724K. We warmly invite brothers, sisters, and ministry partners who care about the development of the LOGOS campus to support the final-stage needs of the Phase III Campus Redevelopment.

SUPPORT PHASE III Give Now
PHASE III VIDEO

Learn About the Phase III Project

Watch the video to learn more about the Phase III project, the campus spaces, and the vision behind the development.

PROJECT TIMELINE

Phase III Major Construction Milestones

From initial planning, municipal applications, bidding, and groundbreaking to structural construction, exterior completion, interior improvements, and the anticipated opening date, the following timeline highlights the major milestones of the Phase III project.

CURRENT PROGRESS
Current Status: Fourth-Floor Structural Construction
AS OF APRIL 2026
01 · PLANNING & APPROVAL
2017

Planning Began

Completed
Began in November 2023

Construction Bidding

Completed
Obtained in May 2025

Municipal Application and Approval

Applications proceeded through several stages from 2020 to 2025. The final building permit was obtained in May 2025.

Completed
JULY 2025

Construction Began

Completed
AUG 2025

Groundbreaking Ceremony

Completed
NOV 2025

Foundation Completed

Completed
02 · STRUCTURAL CONSTRUCTION
JAN 2026

First-Floor Structure Completed

Completed
MAR 2026

Second-Floor Structure Completed

Completed
MAY 2026

Anticipated Third-Floor Structure Completion

Planned
03 · NEXT PHASE
DEC 2026

Anticipated Exterior Completion

Planned
MAY 2027

Anticipated Interior Completion

Planned
AUG 2027

Anticipated Opening

Planned
SUPPORT PHASE III

An Invitation to Participate in Phase III Campus Redevelopment

The Phase III Campus Redevelopment is a vital part of LOGOS Evangelical Seminary’s campus renewal plan. We warmly invite brothers, sisters, and LOGOS partners who care about the Seminary, theological education, and campus development to support the Phase III project through their giving. Your participation will be an essential part of bringing this project to completion.

Thank you for your care and support for the LOGOS Evangelical Seminary Phase III Campus Redevelopment.

PARTICIPATE · SUPPORT · BUILD

Partner with LOGOS in completing the final phase of our campus redevelopment.

SUPPORT LOGOS Give Now