Phase III Campus Redevelopment Construction and Fundraising Progress
The Phase III Campus Redevelopment is the final phase of LOGOS Evangelical Seminary’s campus renewal plan.
Following earlier renovations to the Administration Building, Academic Building, classrooms, and library, Phase III will bring the Seminary’s comprehensive campus redevelopment plan to completion. This page provides updates on construction progress and the final stage of fundraising, allowing donors and partners who care about the development of the LOGOS campus to stay informed about current progress and remaining needs.
Upon completion of Phase III, LOGOS Evangelical Seminary’s comprehensive campus redevelopment plan will reach its final stage.
Building Space Plan
The Phase III building is located directly across from the Administration Building. It is planned as a four-story, multipurpose facility integrating parking, the main entrance, student life, campus fellowship, administrative offices, workspaces, meeting rooms, and other campus needs.
Phase III will bring together a wide range of campus spaces, including a student activity center, Seminary history gallery, fellowship lounge, dining area, prayer room, production studio, Student Affairs offices, and additional office and meeting facilities.
Construction Funding
The original estimated total construction cost was $13.54M, including the building, interior improvements, equipment, and design. Fundraising for this amount has been completed. Following the 2025 wildfires and the effects of inflation, the project is expected to require an additional $1.0M in funding.
Final-Stage Additional Funding Progress
As of August 2026, the additional funding goal still requires $724K. We warmly invite brothers, sisters, and ministry partners who care about the development of the LOGOS campus to support the final-stage needs of the Phase III Campus Redevelopment.
SUPPORT PHASE III Give Now →Learn About the Phase III Project
Watch the video to learn more about the Phase III project, the campus spaces, and the vision behind the development.
Phase III Major Construction Milestones
From initial planning, municipal applications, bidding, and groundbreaking to structural construction, exterior completion, interior improvements, and the anticipated opening date, the following timeline highlights the major milestones of the Phase III project.
Planning Began
Construction Bidding
Municipal Application and Approval
Applications proceeded through several stages from 2020 to 2025. The final building permit was obtained in May 2025.
Construction Began
Groundbreaking Ceremony
Foundation Completed
First-Floor Structure Completed
Second-Floor Structure Completed
Anticipated Third-Floor Structure Completion
Anticipated Exterior Completion
Anticipated Interior Completion
Anticipated Opening
An Invitation to Participate in Phase III Campus Redevelopment
The Phase III Campus Redevelopment is a vital part of LOGOS Evangelical Seminary’s campus renewal plan. We warmly invite brothers, sisters, and LOGOS partners who care about the Seminary, theological education, and campus development to support the Phase III project through their giving. Your participation will be an essential part of bringing this project to completion.
Thank you for your care and support for the LOGOS Evangelical Seminary Phase III Campus Redevelopment.